March 2002
Who Drained the Everglades?
The Same Folks Who Are Now Restoring Them
By Clay J. Landry
President George W. Bush and Florida governor Jeb Bush recently
signed an agreement affirming that an $8 billion, 30-year federal plan
to repair the Everglades will at least partially restore the natural
flow of water through the wetlands. But environmentalists should not
rest easy. The job of restoration is being handed over to the entity
that was most responsible for the problem in the first place: the
federal government, and, in particular, the Army Corps of Engineers.
The Everglades today receives less than one-third of its historic
water flow, the water is contaminated by fertilizer and other runoff,
and the wildlife-rich wetlands are half the size they were when the
federal government started its draining projects in the 1920s. The story
of the Everglades epitomizes government programs gone awry. It also
shows that the private sector, however ambitious, is restricted in the
environmental harms it can cause. The need to cover costs reduces the
potential for massive mistakes. Even state governments are limited in
the harm they can cause. But the federal government is able to override
common sense and cause environmental havoc.
Early settlers to Florida wanted to drain the Everglades, a swampland
covering about 4000 square miles in south Florida. The goal was to
create farmland by digging canals that would draw off the swamp water
and allow it to flow to the ocean. Most people thought that draining the
Everglades would be as simple as pulling the plug in a bathtub (Blake
1980, 4). But the undertaking proved too costly, even with early help
from the state and federal governments.
Governmental help started with the federal Swamp and Overflowed Lands
Act of 1850, which gave the state title to all "swamped and submerged
land" that it could reclaim (Carter 1974, 58, 60). The Florida
legislature quickly began encouraging settlement of an area near Lake
Okeechobee, most of which was part of the Everglades. It formed the
Internal Improvement Fund (IIF), a state agency that used public money
to entice private developers to drain land.
The IIF had a sordid history, peppered with accusations of corruption
and underhanded dealings, excessive construction costs, and poor
investments. Even though a wealthy industrialist from Philadelphia saved
it from bankruptcy at the end of the nineteenth century by purchasing 4
million acres of submerged land, extensive development proved virtually
impossible. By 1920 fewer than 900,000 acres had been successfully
drained. Florida’s reclamation efforts were paralyzed by financial
failure.
Unable to collect drainage taxes, borrow more money, or meet bond
payments, the state turned to federal aid, specifically to aid from the
Army Corps of Engineers, the only federal agency equipped to undertake
such a grandiose task as draining the Everglades. One of the first
projects undertaken by the corps was a flood control project on Lake
Okeechobee, largely in response to the flooding and tragic deaths caused
by hurricanes in 1926 and 1928. Many people blamed the catastrophic
flooding on poorly designed and unfinished drainage projects left by
early developers. To alleviate future flooding, the corps constructed
the Herbert Hoover Dike, which was eighty-five miles long and at least
three times the size of the old state-built mud levee. In total, the
project cost just over $19 million, about twice the original estimate.
Florida was initially required to kick in $2 million for the flood
control project, but Congress reduced the state’s obligation to $500,000
when it was unable to raise the money (McCally 1999, 140).
The National Industrial Recovery Act of 1933 gave President Franklin
Roosevelt the authority to spend an unprecedented $3.3 billion on
construction projects (Blake 1980, 147), and the Florida delegation
quickly launched a campaign to fund the Cross-Florida Canal project.
Building a canal across Florida had been a pet pork barrel scheme since
Congress first allotted money for it in 1826 (Blake 1980, 151).
President Nixon finally killed the project in 1969.
By 1950, the federal assault on the Everglades was in full operation.
In 1947, one of the worst storms on record had flooded nearly 2.5
million acres (General Accounting Office [GAO] 1999, 3), and in 1948
Congress approved a bill for $208 million to provide flood control for
700,000 acres (Kriz 1994, 590). The money initiated the Central and
South Florida Flood Control Project, a system of more than 1,700 miles
of canals and levees and sixteen major pumping stations (GAO 1999, 4).
This project drains lands south of Lake Okeechobee that is now farmed
primarily by sugar growers. Completed in 1979, the project arrived ten
years past its deadline and nearly $100 million over budget (Snell and
Boggess 1994, 21).
And it left environmental problems in its wake by severely disrupting
the flow of water in the Everglades. Signs of environmental trouble
became visible in the summer of 1966, when heavy rains forced extensive
pumping of excess water from farmlands. The water was deposited on land
that was reserved for wildlife and home to much of south Florida’s deer
population. Hundreds of deer drowned and smaller animals like wild hogs
and raccoons died because high water covered their food supply.
Today, levees and drainage canals continue to block the flow of water
through the Everglades, including Everglades National Park. During years
of adequate rainfall the park has enough water, but in dry years, water
is held in drainage canals and diverted from the park. The park is last
in line in the 250-mile system and thus at the mercy of other uses, from
flood control for agricultural lands to municipal water demands.
In some years too much water is a problem for the Everglades. After
large rainstorms, water control districts relieve flooded farmlands by
releasing large volumes of fresh water in brackish estuaries adjacent to
the park. The excess water disrupts the delicate mix of brackish water
needed to produce shrimp and fish, a food source for many coastal birds.
When these aquatic creatures are not abundant, coastal birds will desert
their nests and nestlings in search of new food supplies, farther away.
Water drainage and control, paid for largely with federal funds,
opened the door for commercial sugar production in the Everglades. No
single policy affected the development of the Everglades more than the
sugar embargo on Cuba. In 1960 fewer than 50,000 acres of sugarcane were
planted in all of Florida; but domestic sugarcane growth exploded from
1961 as Cuban sugar was entirely eliminated from the U.S. market. During
the embargo Florida’s sugar acreage production increased nearly
fourfold, from 50,000 acres in 1959 to more than 200,000 acres five
years later.
Furthermore, federal price supports ensured that more land would be
drained and planted in sugarcane. Domestic sugar prices are supported by
the federal government through a complex arrangement of loans and import
restrictions. These programs have effectively kept domestic prices well
above the world price.
By keeping sugar prices high, federal policies encourage farmers to
achieve high yields through extensive use of fertilizers and chemicals.
The buildup of fertilizer is particularly harmful. Phosphorus, a
chemical not abundantly found in the region’s natural water supply, is
leaching into groundwater that is then pumped to Everglades National
Park and Loxahatchee Wildlife Refuge.
Studies estimate that nearly 80 percent of phosphorus used in
fertilizing crops reaches the Everglades (Coale, Izuno, and Bottcher
1994). Nonnative plants that thrive on the phosphorus (such as cattails)
are crowding out naturally occurring species (such as sawgrass). Bird
populations are only 10 percent of what they were at the turn of the
century (Tolman 1995, 3, 6–7), primarily because of habitat loss to
sugarcane production and reductions in food sources due to polluted
runoff.
Sugar policies remain in force despite a coalition of environmental
and fiscally conservative taxpayer groups opposing them. Rather than
change these policies, Congress is taking a familiar tack—more pork
barrel. To rectify years of federal abuse, Congress has authorized the
Army Corps to begin what has been touted as the largest environmental
restoration effort undertaken in the history of the United States. The
basic idea of the plan is to capture fresh water that has been flowing
to the ocean, store it in new reservoirs, and then release some of it to
mimic the natural flow of the Everglades. The remaining water will be
diverted to meet the needs of sugar plantations and thirsty cities
throughout southern Florida.
While public rhetoric highlights the restoration phase of the
project, critics such as Environmental Defense and the Natural Resources
Defense Council charge that, like so many corps projects, the water
supply features of the plan dominate restoration efforts. It was to
allay these fears that the president and the Florida governor agreed to
give a high priority to restoring natural flows. Time will tell whether
the result will be mostly restoration or mostly pork. |